万平嘉园二期施工简报(第四期)  

2011-06-12 19:02:05|  分类: 默认分类 |  标签: |举报 |字号 订阅

  下载LOFTER 我的照片书  |
 

                      万平嘉园二期施工简报(第四期

                                                  (海南万平房地产开发有限公司总工办·主办)


                                        2011年6月12日  星期日        编辑打印发行:张 涛  审核:孙善修


······························································································································································

 

本期目录:

(1)   一周保亭天气

(2)   6月份第二周工作总结及第三周工作计划

(3)   万平网转载:海南万平四项措施改变职工居住条件

(4)   万平网转载:·临沂市原人大副主任李甫到海南万平检查指导工作

(5)   二期挖桩孔9米深遇到花岗岩状况及判断

(6)   总工办发文:“关于16个桩孔遇到花岗岩判断及继续下挖”的通知

(7)   “关于万平嘉园二期分包定位及工期控制三步走”会谈纪要

(8)   王贵梓、杨连福委婉思想工作:以工程大局为重

(9)   《万平嘉园二期建设工程施工许可证》申报材料准备情况

(10)  认真学习《集团6.11通知》,继续反映万平嘉园精神风貌

 

···········································································································································································

                                                一周保亭天气情况

(1)   本周天气晴,11日下午雷阵雨;12日下午4点雷阵雨;

(2)   本周气温,白天35度,夜间24度。

 

······································································································································································

                          6月份第二周工作总结及第三周工作计划

一:6月份第二周工作总结

(1)因施工方因“4.29提土桶坠落”及“5.31工人摩擦”施工长达一周停滞状态于6月4日结束;为保持刚恢复施工后的稳定,又面临保亭6-9日高考,工程及预算人员端午节照常上班。

(2)本周挖桩孔人员在34人左右,完成挖桩孔234米,平均每天33米,完成本周计划的65%;本周挖孔桩9米左右遇到花岗岩累计16处,仍不判断为持力层;总工办发文:《“关于16个桩孔遇到花岗岩判断及继续下挖”的通知

(3)面临6-9日保亭高考,有关部门禁止高考期间施工;经协调二期挖孔桩无噪音,得到许可;

(4)为解决施工工人住宿困难,总工办、预算室、工程部、资料室板房办公室腾迁给施工方使用。

(5)二期报建资料准备完成,将于15日报送办公室准备办理有关报建事宜;

(6)6.9刘吉华经理主持建设、施工协调会,分包定位待确定,“二期工程工期控制三步走”基本确立。

 

二:6月份第三周工作计划:

(1)督促施工方尽快绘制《二期花岗岩桩位图》对照《地质勘探报告》,以期作出准确判断;

   (2)配合办公室进行二期报建资料的完善工作;

   (3)启动一期备案资料顺理,继续完善一期有关工程细部工作。

 

                                                                                                  总工办暨工程部

                                                                                                   2011年6月12日

 

·································································································································································


                                  海南万平四项措施改变职工居住条件

                                   来源:万平网 发布时间:2011-06-10 查看次数:32


    进入夏季以来,海南万平房地产开发有限公司认真落实集团主要领导关于“人性化”管理的有关指示和要求,积极采取措施为职工解决生活中的困难,努力改变职工居住条件,提升了公司良好形象。
    一是组织力量对万平嘉园部分房间进行简装修,由办公室统一调整安排,让在外租房的职工搬进宽敞明亮的新楼房,“家”的感觉得到体现。
    二是根据实际情况在职工宿舍安装了空调,解决了职工因天气太热睡不好觉、不能正常休息的问题,也间接提高了工作效率。
    三是统一配备床铺、床垫、床头柜、布衣柜等生活用品,实行半军事化管理,使员工们住起来舒心、用起来方便,居住环境看起来干净整洁,逐步建立了良好的生活作风。
    四是制定了相应的规范管理制度,努力保障职工人身和物品安全,并促使形成了节水、节电的良好习惯。
(办公室)

·····································································································································································

《万平网》转载:


                        ·临沂市原人大副主任李甫到海南万平检查指导工作
6月11日临沂市原人大常委会副主任李甫在海南万平公司副经理刘吉华陪同下到海南万平嘉园检查指导工作。期间李主任先后察看了我公司售楼中心、万平嘉园二期工程施工现场,并与公司部分中层干部进行座谈。李主任对万平近年来的快速发展和巨大变化给予了高度评价,同时也提出了宝贵意见。
                                                                                                            (办公室)

 

···································································································································································

                                                二期挖桩孔9米深遇到花岗岩状况及判断

   6月11日施工方易茂福、监理方李三春、韩宝德、建设方孙善修、王家富、张涛就万平嘉园二期16个桩位出现花岗岩问题进行分析认为:目前仍不做持力层判断,要绘制《花岗岩桩位分布图》,对照《地质勘探报告》做出准确判断,以防判断失误,造成工程隐患。分析判断如下:

一:E栋区域:

 (1)进展情况:区域共60根桩位;最深14米,最浅5米,平均深9.5米;15天内未挖16个;

(2)目前遇到花岗岩桩位共9个:2#桩位8.5米;3#桩位11米;5#桩位9.5米;17#桩位9米;20#桩位9.5米;22#桩位10.5米;24#桩位9米;50#桩位8.5米;53#桩位8.5米;

(3)基本判断:(1)2#桩位与3#桩位相邻,出现花岗岩悬差2.5米,判断为孤石;(2)区域内60个桩位,出现花岗岩桩位9个,且基本桩位只有5米,不做持力层判断。

二:F栋区域:

(1)进展情况:区域共18根桩位,最深11米,最浅6米,均深9.5米;

15天内未开挖9个;

(2)目前遇到花岗岩桩位2个:2#桩位9米,14#桩位6.5米。

(3)基本判断:18个桩位仅有2个出现花岗岩,出现比率仅为10%,且有停在6-9米得桩位9个,判断为孤石。

三:G栋区域:

(1)进展情况:区域共桩位51个,最深11米,最浅7米,12天内未开挖停留在7-10米的8个;

(2)目前遇到花岗岩桩位5个:1#桩位9米;2#桩位8米;16#桩位9米;21#桩位9米;41#桩位8米;

(3)基本判断:51个桩位仅出现5个,出现比率进约10%,不做持力层判断。

                                                                                            (供稿:王家富、张涛)

---------------------------------------------------------------------------------------------------------------------------------

               海南万平房地产开发有限公司总工办文件

                                                       琼万工字(2011)第028号

---------------------------------------------------------------------------------------------------------------------------------

                       “关于16个桩孔遇到花岗岩判断及继续下挖”的通知

   根据6月11日监理、施工、建设施工例会研讨意见,万平嘉园二期16根挖桩孔遇到花岗岩,经研讨判断仍为孤石,要求继续下挖,并对照《地质勘探报告》编报《当前花岗岩桩位图》,以期进行准确判断。

附件:《6.11施工例会纪要》:

时间地点:6月11日上午9-11点,四建现场办公室:

建设方参加人:建设方:孙善修、王家富、张涛;监理方李三春及施工方易茂福等4人

纪要内容:下午2点32分短信:“6.11施工例会纪要:(1)E栋共60桩,其中9根深在8.5-11米遇到花岗岩,相邻2#桩深8.5米,3#桩11米,判断为孤石,15天未挖停在5米的1个,7-11米的15个;(2)F栋共18桩,最深11米,15天停在6-9米9个,14#桩6.5米遇到花岗岩,判断为孤石;(3)G栋共51桩,最深11米,12天停在7-10米为挖8个,遇花岗岩5个,深在8-9米间,仍不做持力层判断;(4)会议研究认为应继续下挖;会议要求半月33根桩无人挖应增加人员;会议提出8.6是嬉水节,要充分考虑七仙河7月下旬蓄水影响,关注±0.00施工都在雨署季节的情况;会议同意塔吊桩基已11米不再下挖;(5)要求对照《地质勘探报告》编报《当前花岗岩桩位图》,以防判断失误。孙。”;发黄立宾\易茂福\李三春\韩宝德\王家富\杨通国\黄春义;并报告张振勇\彭超\刘吉华\杨连福\王贵梓\杨克安及刘总。

特此通知.

 

                                                                                           海南万平房地产开发有限公司总工办

                                                                                                         2011年6月11日

 

主发:工程部、预算室、四建公司、海瑾监理各1份

主报:张总、彭总、刘吉华经理及刘总各1份

存档:总工办存档1份

·························································································································································································

 

                        “关于万平嘉园二期分包定位及工期控制三步走”会谈纪要

  时间地点:6月9日上午10点-11点40分在刘经理办公室

  参加人:施工方:黄立宾;建设方:刘吉华、王家富、孙善修

 纪要内容:

(1)下午1点04分孙善修短信及时通报内容:“张彭总刘经理并黄立宾经理:今天上午10点刘经理主持万平嘉园二期施工推进会会谈纪要:(1)关于施工方定位问题:刘告诉黄:“分包方为山东龙奥,劳务资质。”黄未同意说:“劳务资质多的是,我们用海口四建。”(2)关于嘉园二期工期:会谈确定了工期控制三步走方案:第一阶段:±0.00以下由原7.20确定为9.20;第二阶段:主体封顶包括二次结构2012.1.31完成,保证春节开盘;第三阶段:2012.5.1竣工交验。“嘉园二期工期三步走计划”会谈双方确认。(3)会谈施工方黄立宾、建设方刘吉华、王家富、孙善修参加。孙。”主发黄立宾、张振勇、彭超、刘吉华;并发李三春、韩宝德、易茂福、王家富、杨通国、毛海洋、王贵梓、杨连福及刘总。

(2)下午1点短信中及时通报的内容:(略)

······

(3)晚8点《“关于万平嘉园二期分包定位及工期控制三步走”会谈纪要》邮箱报送有关领导;

(4)晚9点同杨连福经理就短信未通报内容谈“属于策略性”看法,杨经理认为认同此看法。

                                                                                   (摘自《总工办工作日志》

 

························································································································································································

 

                                        王贵梓、杨连福委婉思想工作:以工程大局为重

     6月11日中午,总工接到家中电话:“姑母病故。”当即向刘吉华经理请了事假,刘吉华经理对其返山东行程作出了妥善安排。

当王贵梓主任、杨连福经理知道这一情况,考虑目前挖桩孔出现花岗岩需要继续进行准确判断,委婉向总工进行了“刘吉华经理刚到任时间不长,张振勇总经理又出差在济南,目前工程正处在16桩位出现花岗岩,需要做出准确判断时期,你临行前要对工程部人员详细安排······”,听了王贵梓主任、杨连福经理的一席话。总工当即汇报刘吉华经理退了已订的飞机票。

                                                                                                                      (张涛   供稿)

························································································································································································

                                    《万平嘉园二期建设工程施工许可证》申报材料准备情况

1、              建设工程施工许可申请表;                      填写

2、              建设用地规划许可证(规划内项目);             已有

3、              建设工程规划许可证(规划区内项目);           已有

4、              拆迁许可证或施工现场是否具备施工;       不存在拆迁

5、              中标通知书,招标发包备案证明;                已有

6、             施工合同;                                    待签

7、              工程地质勘查报告、施工图纸及审查合格证书;    已有

8、              工程预算书;                            预算部负责

9、              施工组织设计;                                已有

10、          施工企业资质证书、营业执照、安全生产许可证及项目施工管理人员配置情况及资质证书、省外建筑企业进琼等级手续;

                 其中:资质证书、省外建筑企业进琼登记→由办公室负责;项目施工管理人员配置情况及资质证书→由黄立宾负责;

11、          工程监理合同;                                已有

12、          监理单位资质证书、营业执照和项目监理管理人员配置情况,资质证书                                      已有

13、          质量安全监督手续;                        办公室负责

14、          资金保函或证明                            财务负责

15、          工程以外保险办理证明                    黄立宾负责

16、          农民工工资保证金缴交证明;              黄立宾负责

17、        消防部门的消防报建审核意见书和防雷装置设计核准书;杨通国负责

                                                                                                (黄春义  供稿)

                                                                                                      2011-6-8

·····························································································································································································

           认真学习《集团公司6.11通知》,继续反映万平嘉园精神风貌

6月11日王贵梓主任到总工办指示:“集团公司刚下发了《通知》,提出要积极为《万平网》写稿,及时反映万平嘉园风貌”的要求;总工办根据王贵梓主任要求,对自2010年以来积极为《万平网》写稿情况做一基本总结,继续为反映万平嘉园精神风貌而努力。

附件:海南万平总工办2010年以来在《万平网》发表的文章

(一)“7·16康森台风”万平嘉园工地平安
来源:万平网 发布时间:2010-07-17 查看次数:230

以下网址:http://www.sdwanping.com/show.asp?id=3080

 

(二)消除“7·16康森台风”影响,确保“6·25既定目标”施工进程
来源:万平网 发布时间:2010-07-18 查看次数:171

以下网址;http://www.sdwanping.com/show.asp?id=3081

 

(三)万平情系海南岛 确保七夕嬉水节
来源:万平网 发布时间:2010-08-15 查看次数:280
以下网址:http://www.sdwanping.com/show.asp?id=3132

 

(四)嘉园项目添新装 黎苗兄妹共欢唱
来源:万平网 发布时间:2010-08-16 查看次数:393

以下网址:http://www.sdwanping.com/show.asp?id=3133

 

(五)海南49年一遇暴雨来袭,万平嘉园工地平安
来源:万平网 发布时间:2010-10-11 查看次数:356

以下网址:http://www.sdwanping.com/show.asp?id=3252

 

(六)万平嘉园二期工程将于11月16日举行开工典礼
http://shanxiuruifeng.blog.163.com/blog/static/13247343120101012115529642/

注:《万平网》未发表。以上原文

(七)“12.10全力以赴保投产工作思路”一周年,万平嘉园精神又添新篇章

           来源:万平网 发布时间:2010-12-13 查看次数:326
          以下网址:http://www.sdwanping.com/show.asp?id=3855

 

(八)万平嘉园新年新气象,全力推进确保竣工交付

默认分类 2011-01-01 07:07:52 阅读2 评论0   字号:大中小 订阅

注:本文2011.1.1已发表在《万平网》上,后集团公司郝志主任通知修改为:

见网址http://www.sdwanping.com/show.asp?id=4054

 

(九)要理直气壮的弘扬“万平嘉园精神”:

见孙善修2011.1.13及14手机短信报告张振勇、彭超、杨克安、刘玉芬、李广耀及刘总:(未发表)

                                                                                                   摘自《海南万平总工办工作日志》

 

(十)全国人大代表世界知名玉米育种专家李登海先生莅临万平嘉园
                      来源:万平网 发布时间:2011-04-05 查看次数:143

             以下网址http://shanxiuruifeng.blog.163.com/blog/getBlog.do?  

             bid=fks_095064082085085068084081081095085085083071083085082064085

 

(十一)您当前位置:网站首页 >> 文苑荟萃 >> 阅读文章

          扬正气、促和谐,唱响“万平嘉园二期建设又好又快”主旋律
                          来源:万平网 发布时间:2011-05-28 查看次数:58

               以下网址:http://www.sdwanping.com/show.asp?id=5589

 

(十二)您当前位置:网站首页 >> 文苑荟萃 >> 阅读文章

              海南万平房地产公司关心施工队伍推进二期建设
                      来源:万平网 发布时间:2011-06-06 查看次数:65

                以下网址:http://www.sdwanping.com/show.asp?id=5643

 

                                                                                                             (供稿    张涛辑)

···················································································································································································